Jonny A.
Norconsult is asking for drawing of container with meassurments,  plan and cross sections
Denis S. It is a standard 40 feet highcube container with standard fittings
Denis S. Is this information enough?
Jonny A. I found a picture on the web with measurements and sent it to them. If they need more I will contact you again.
Jonny A.
I have sent the translation og the electrical schematics to NØES.
Denis S. 👍
Jonny A.
Stein Solbu (new leader of Nordavind DC) will replace Arild in the meeting on Hamar.
Arild will attend the rest of the meetings.
Jonny A.
Norconsult have sent the application stage 2, for the buildings to the plan and building Office.
Jonny A.
If you give me the number of switches you need and the wanted model, I can check prices for you.
Denis S. HPE 1910 48 Switch
Denis S. 10 pcs
Denis S. Please send a copy documents you will have after parcel from China will be received
Denis S. All of them
Denis S. The ones that we in the box
Denis S. And you will have from DHL
Denis S.
Jonny A.
HPE 1910 is end of life, the replacment are these two:
(All of these are Officeconnect, not Enterprise.)

HPE OfficeConnect 1950
https://www.hpe.com/us/en/product-catalog/networking/networking/pip.hpe-officeconnect-1950-48g-2sfpplus-2xgt-switch.6887557.html

HPE OfficeConnect 1920S
https://www.hpe.com/us/en/product-catalog/networking/networking-switches/pip.specifications.hpe-officeconnect-1920s-48g-4sfp-switch.1009689667.html


I would use Aruba 2530-48G (new HP switch enterprise)
https://www.hpe.com/us/en/product-catalog/networking/networking-switches/pip.aruba-2530-48g-switch.5333809.html

Check with the IT-department wich one that is most fitting for you, and I will suply you with the prices.
Jonny A.
t
Jonny A. I have sent you the documents by email.
Jonny A.
We need drawings with meassurments of how the containers will look inside, when they are fully operational.
Is it OK to spilt the wardrobe in two (need separat for men and women). this may increase the cost, but not with much. We also need a room allocated for cupboard. Do you want a new offer with these changes, or should we just push forward?
Jonny A. We also need an explanation for why there is only four offices, when it can be up to ten workers. Will there be added more sections or is the idea shift workers?
Denis S.
We need drawings with meassurments of how the containers will look inside, when they are fully operational. 
Denis S.
I have uploaded a drawing of container with miners inside
Denis S.
Please go ahead with changes of wardrobe and a room for cupboard
Denis S.
Office space - we will increase the number of employees gradually, when we would need more space we will erect another building or upgrade existing one. Another point is that some employees of Data Center will not have the dedicated desk - electricians and it support. It means that with four desks we would be able to offer jobs to eight employees.
Jonny A.
NØK asks if it`s OK to place the four first containers on the four places farthest North?
This is for avoiding cable crossing and limit the length of the low voltage cables. 
Denis S. It doesn’t matter for us
Jonny A.
Some questions that came up after the last meeting.
- The locks for the containers are they ment for stoping the container moving or against theft?
- When do you want the fence in place? 
- Do you want Norconsult to handle the budget regarding NØK?
Denis S. Locks - are against droning
Denis S. Fence - early may
Denis S. Norconsult - NOK - no
Denis S. Please make photos of current progress on the plot
Denis S. Photos - no rush
Jonny A.
Information after the last meeting.
- NØK will have power on the first transformer ca. April 25th.
- Tronfjell Maskin will probably have the pillars for the first container ready April 25th. 
- We had too scrap the building we planed to use as the office building, Tronfjell Maskin are awaiting drawings/offers from another supplier.
- As soon as we have the office building drawings/costs in place, and your approval, we will send the application to the Labour Inspejction for their approval. We hope to have this ready wednesday/thursday.
- New pictures from the plot will be uploaded shortly
- Norconsult gave me new information about documentation Dataroom AS needs regarding work at the plot. It`s not something that stops the project in any way, but if there is an accident at the plot and this is not in place, there can be issued fines or more serious consequences for the people registered as owner/manger. I have asked Norconsult for an offer regarding this.
Jonny A.
Droning, do you meen vibration sounds like a buzz? 
Denis S. I mean - kantre
Jonny A.
I`m sorry but you need to explaine.
Denis S.
Denis S. Keep it from falling on the side
Jonny A. Now I understand 👍
Jonny A.
The pillars have a steel plate on top, Norconsult suggest to weld the container to this. This will lock the container and prevent it from tipping over. 
The container will then also function as a  strut for the pillars.
Is this OK?
Denis S.
Ok
Jonny A. The new application to Labor Inspection has just been sent.
Denis S. 👍
Jonny A.
Norconsult is asking about how you want the ourdoor areas to be?
- Do you want green ares? Where?
- Will there be any heavy transport to the containers after they are placed? Do you want the ability to drive close to the containers on all sides?
- Do you want all of the area inside the fenced area to be road?
Denis S. Inside the fence all area to be road
Denis S. Green areas will be thinking about green areas in a year or so:)
Jonny A.
What do you want to do with the areas outside the fence and office building?
Green, gravel etc.?
Jonny A.
Jonny A.
Jan Erik is asking if this fence is ok?
It`s cheaper and easy to move around. But it has bigger spaces underneath, also easy to remove.
Jonny A.
Norconsult have spoken with the Labor Office today.
Labor Office haven`t had time to look at the Application yet, they assumed that they would get time for it on tuesday or wednesday.
Jonny A.
Østa Elektro does not see any problem With the Leagrand Curcuit breaker. I have added some calculations I got from them under Technical information.
Denis S. Great, thanks! I will send it to container producer
Jonny A.
The company that delivers the office building, can have it ready for delivery earlie week 35.
Do we handle this our self, or do we use Tronfjell Maskin for it?
Denis S. What do you mean handle by ourselves?
Jonny A.
It is the same as the one we got an offer for earlier. To be sure to get it, we have to reserve it as soon as possible.
Who makes the reservation, Fjell IT or Tronfjell Maskin?
If you have decided to still use Tronfjell Maskin, I would recomend that they handle this.
Jonny A.
CCTV and using installation/parts from third party supplier:
Relisec says that the alarmsystem should be jablotron, but regarding the cameras we can use almost everything. But they must be involved when the analysis is done.
Regarding the question of the three offers we asked for, they need the updated plot map. I will send it to them as soon as we have gotten them for Norconsult and you have approved them.
Denis S. Jonny, hello! Any news on office building?
Jonny A.
I have uploaded the English version now. and the new plot map from Norconsult.
Norconsult also asks for the drawings for the new containers, included measurements and cross section drawings.
Jonny A.
Uploaded one offer on shipping of Storage container. I guess the summer holiday is the reason that we have only one offer so far.
Denis S. Ok, let’s wait till end of July to get more offers
Jonny A. The supplier of the Office building will give 10% discount after 1 year lease time.
Jonny A.
Information from Norconsult:
- We need your approval of the updated plot map, or changes you wan`t.

- I guess these containers make more noice, because of the higher number and fans. We therefore must make a new noice measurements. Can you send the necesary information for the new containers, so Norconsult can do the  new measurements.

- We need a new approval from the neighbours (neighbour Notification). 
This time we send it as registered mail, they have two weeks to reply from they recieve the notice. If they don`t reply, it`s the same as "I accept".

- We have to re-apply to the Bulding Office at Tynset Kommune, since the number of containers have increased.
Denis S.
Plot map is ok
Denis S.
The containers are much less noisy. In the first container, we had 1000 units each producing 65dB and the container is open on each side. The new container accommodates 252 units each producing 65dB and the container is closed and some fins.
Denis S.
Overall noise level will be much lower
Denis S.
We have to re-apply to the Bulding Office at Tynset Kommune, since the number of containers have increased. 
Denis S.
Please re-apple
Jonny A.
Norconsult needs confirmation that we continue With Tronfjell Maskin. They need this for the New Application to the bulding Office.
Denis S. I confirm that we continue with Tronfjell Maskin
Jonny A.
Jonny A.
I recieved a New drawing from Østa Elektro.
Jonny A.
The Applications With the changes have now been sent to the Building Office. No neighbours had any comments within the deadline that was given to them.
Denis S. 👍
Jonny A.
Hi.
Relisec is unable to Connect the cameras inside the containers to their CCTV system, because the cameras don't support ONVIF. 
August 3rd I updated you on the requirements from Relisec to Connect other cameras to their solution.
I updated you in the comment area under their offer. 
Do you want to change cameras or leave it as it is? 
Denis S. Leave it as it is
Jonny A.