Alvdal, Norway

Jonny Andersen mobile subscriptions — Hello. The Norwegian mobile subscriptions from Telia is registered to Fjell IT AS, this means that I get the invoices. Is it OK if I transfer ownership of this to Dataroom AS? 1
Jonny Andersen Approval by Alvdal municipality — We now have the approval to start up the site :-) We don`t need to reaply for the next lines og containers, as long as all containers are in accordance with given permission.  [MELDING OM DELEGERT VEDTAK MIDLERTIDIG BRUKSTILLATELSE GNR._BNR 24_10.PDF] 6
Jonny Andersen Operation of the site — So far we have powered up shelf 6 of miners and done testing and training. Today we will Power up the rest of the miners inn all Three containers. Do you want the site to be in full operation by the end of today, or leave it off. We don`t have an approval to start mining yet, Norconsult has sent... 1
Jonny Andersen Fence — Have you decided when the fence will be put up and how many gates there shall be? Three out of four visits to the plot I have made lately, there have been cars driving on to the plot to have a look and drive back out.  Relisec is asking me about when the installation of the CCTV can happen, and... 22
Jonny Andersen Water and Sewage — Do you want TM to start with water and sewage for the Office building? 5
Jonny Andersen Winter is coming — Suddenly winter is upon us, it could be clever to have all groundwork that includs dirt, gravel, toplayer, digging, tubes and cables done by this time. What to you think, and do you have a plan for delivery of more containers and miners? Winter can start as early as Oktober. 1
Jonny Andersen Things that may "pop" up. — Hi. Questions/information. 1. We are now getting closer to the finish line with getting three containers ready, Office building an so on. The absolut deadline for the containers to be ready is 2nd of september and the miners should be installed by the 12th of september. In my experience there ca... 1
Denis Slabakov, New Mining Company Network setup — Jonny, please check availability of following products to be installed into admin building Mikrotik | CRS328-4C-20S-4S+RM Mikrotik | CCR1009-7G-1C-PC 19
Jonny Andersen Progressplan and known work for this week (so far). — - TM said that they will be done with the top gravel on the container area, during tuesday - TM said that they will be done with cable trenches for the first line of containers, during thursday - TM have to do a few extra hours of work, because the area that is ment for the Office building is t... 5
Jonny Andersen Adjustment of conatiner — Østa wants a bigger intake hole into the container, is it OK? We have to put on some kind of metal protection for the cables going up the container side and inside through the intake. 6
Jonny Andersen Foundation — To fix the foundation for the three containers, TM needs to do some extra work. That work will be invoiced according to the hourley rate agreed on earlier. There will also be placed metal plates under each corner of every container (for the one arrived today and the two arriving tomorrow + all f... 3
Jonny Andersen Crane — Hi. The Crane TM used today, is busy tomorrow. They have to rent a bigger crane, so there can be some extra cost`s because of this. I don`t know what the exact cost will be yet. This is because the containers arrived sooner than expected, and when TM tried to reserve for thursday, the crane was... 1
Jonny Andersen Containers for storage — I`v heard nothing from shipping Companies, regarding transportation of containers.  I have a Meeting With Norax at Tynset later today, to see if they can produce containers or something similar that we can use for storage. Hopefully they can produce it cheaper than what we have to pay for the con... 2
Jonny Andersen Top layer/Foundation for containers — Question about placing of the containers. It would be ok to set the containers where they are supposed to be when they arrive, so we don`t have to move them later on. But first we have to have the top layer at the spot where they are supposed to be. Can I check if it`s possible for Tronfjell Ma... 1
Jonny Andersen New building application with the changes — This application was sent on August 3th. Normal treatment time is three weeks, but we got a feedback that they probably would be finished this week.
Jonny Andersen Top layer at the plot — Do I have Your permission to tell tronfjell Maskin to start the preparations for the top layer, so they can start With this as soon as we are done With the cable pits/trenches? 3
Jonny Andersen Fiber connection to containers — How do you wan`t them connected? - Each container connected to the Office building? - All containers connected to one Main container? - Daisy chaining? 6
Jonny Andersen Number and placement of cameras — Earlier we spoke of: - Two cameras inside each container - Two - four camera outside each container - Only alarm if door to container or Office building are breached, Not movement outside at the plot. Suggestion: - Suggest that we also use two - four cameras With motion detection inside the Offi... 1
Jonny Andersen Fire protection, police and CCTV — FIRE: - Do you have an automated fire protection system in the containers? - If you have, is it possible to connect a device on the output to this system, that automaticly calls the fire Department when the alarm goes? (the Devices will be delivered by fire alarm supplier). - Is the automated f... 3
Jonny Andersen Top Cover — Tronfjell gave an offer of this in April, and it`s the same offer that they use now. Do you want a fixed price on the work? 1
Denis Slabakov, New Mining Company Earthing and Lighting protection — Jonny, please check with Norconsult what type of information they need to design a plan for earthing the container and lightning protection. The comment from Russian colleagues is that secondary ground loop is required with a resistance of not more than 4 Ohm.   1
Denis Slabakov, New Mining Company Container connectivity — Jonny, please check with a potential contractor for electricity connection on site what type of cable they would recommend to connect the transformer to the container. The power of container is 400 kW, there is one 630A circuit breaker installed inside the container. The distance between transf... 3