Alvdal, Norway

Operation of the site

So far we have powered up shelf 6 of miners and done testing and training.
Today we will Power up the rest of the miners inn all Three containers.

Do you want the site to be in full operation by the end of today, or leave it off.
We don`t have an approval to start mining yet, Norconsult has sent the Application for full operation. But we are allowed to do testing With full operation, this testing can be done over several days/week to see if anything is wrong.

If you wan`t the site to be powered up, do you want us to manage it?
If you want us to manage it, what kind of workforce do you want at the site?
- One person is enough?
- One person monday-friday
- One person 1, 2, 3 or 4  days through the week
- Only go to the site when you or Maxim tells us to?

Comments & Events

Denis Slabakov, New Mining Company
Please do the testing of all containers, make sure that all miners are running for couple of hours.

We will wait till we get an approval to start normal operations

С уважением,
Денис Слабаков