Alvdal, Norway

Progressplan and known work for this week (so far).

- TM said that they will be done with the top gravel on the container area, during tuesday

- TM said that they will be done with cable trenches for the first line of containers, during thursday

- TM have to do a few extra hours of work, because the area that is ment for the Office building is to small (It`s not Clear if this is Norconsult or TM`s fault).

- Modules for the office building will start arriving on wednesday, TM will have the top gravel for this area done before this.

- We have to rent a portable toilet, that the workes can use before the Office building is done (demanded by the labor Inspection agency). I have asked the local company that rent these out, for a price.

-Norconsult has meassured where the three first containers are to be placed.
But somehow the placement are not on line with the transformers. Working With TM and Norconsult to fix this (should be an easy fix).

- Østa has not yet replied when they can start connecting the containers. Will update as soon as I have this information.

Comments & Events

Jonny Andersen
Rent for the portable toilet is 4.000,- NOK.
Delivery and pickup is 450,- for each.

There`s included one disposal of content during the lease.
Denis Slabakov, New Mining Company
Ok

С уважением,
Денис Слабаков
Jonny Andersen
Østa estimates monday/tuesday for connecting the first container.

Toilet is ordered and will arrive tomorrow. 
To do it as easy as possible, I registered Fjell IT as the customer. 
I will include the amount of the lease in my NeXT invoice. You will also get the original invoice from the Company I leased it from. 
Denis Slabakov, New Mining Company
Great

Second and third containers - to be connected by end of next week?

What is a status for fiber?

С уважением,
Денис Слабаков
Jonny Andersen
As soon as Østa is finished With the first container, they move on to the second and third.

Fiber will be connected when Nord Østerdal Kreftlag connect the power.