We have recieved confirmation that the plan and building office recieved the building application 22.02.18. The confirmation says that the application must be determined within 12 weeks, by law. They also say that from the moment the application is complete we will have an answer within 3 weeks (neighbour applications wil be sent on tuesday), it probaly meens we will have an answer within 3 weeks from tuesday. I have sent an email to Arild and Per Arne to se what we can do to shorten this waiting period.
The confirmation says that the application must be determined within 12 weeks, by law. They also say that from the moment the application is complete we will have an answer within 3 weeks (neighbour applications wil be sent on tuesday), it probaly meens we will have an answer within 3 weeks from tuesday.
I have sent an email to Arild and Per Arne to se what we can do to shorten this waiting period.