For the permit that allows us to start bulding on the plot, we need more information on this drawing. We need measurements of all rooms, energy consumption and a few other things. Drawing with explanation will then be sent to a goverment organ called "labor Inspection" for their approval. It can take up to four weeks for this approval, it is therefore important that we do this correct at the first try (this is not an application we can influense and shorten the time it takes to get the approval). Norconsult has a dialog With Tronfjell Maskins supplier, to get the necessary information.
It can take up to four weeks for this approval, it is therefore important that we do this correct at the first try (this is not an application we can influense and shorten the time it takes to get the approval).
Norconsult has a dialog With Tronfjell Maskins supplier, to get the necessary information.