Alvdal, Norway

Document Water and sewage v2.docx (18.7 KB)

Download ↓

They want a quick feedback

Comments & Events

Jonny A. posted this on · Download ↓
Jonny A. added a new version on · Download ↓
Denis Slabakov, New Mining Company
Jonny, an increase is by factor 1,5 - it is kind if ridiculous, please check with TM what is exact reason for such a large increase
Jonny Andersen
I know it`s a big difference. 
The reason is that in their first offer, the forgot to include SP1 as shown in the drawing from Norconsult.
I understand that this is frustrating! 
Denis Slabakov, New Mining Company
In first offer is stated - VK1, SP1 and 2
Denis Slabakov, New Mining Company
Please request detailed offer and check pricing of each component is the offer
Jonny Andersen
I`m already working With Jan Erik regarding his offer.
But my priority right now is to get as much training time  With Maxim as possible. OK?
Denis Slabakov, New Mining Company
Sure

С уважением,
Денис Слабаков
Jonny Andersen
Jan Erik stopped by and showed me what his prices are on all the parts that is required for water and sewage.
His cost price is 73.069 + ca. 16.000,- in transportation (transported on two trucks).
J
an Erik will sponsor the insulation for the pipes from kolodets to the building, if it`s needed. 
He uses the same plumber that will Connect the Office building, so they will be able to save some time in coordinating and work hours.
Denis Slabakov, New Mining Company
Ok, I confirm latest offer
Jonny Andersen
Ok.