Jonny, an increase is by factor 1,5 - it is kind if ridiculous, please check with TM what is exact reason for such a large increase
Notified 1 person
Jonny Andersen
I know it`s a big difference. The reason is that in their first offer, the forgot to include SP1 as shown in the drawing from Norconsult. I understand that this is frustrating!
Notified 1 person
Denis Slabakov
In first offer is stated - VK1, SP1 and 2
Notified 1 person
Denis Slabakov
Please request detailed offer and check pricing of each component is the offer
Notified 1 person
Jonny Andersen
I`m already working With Jan Erik regarding his offer. But my priority right now is to get as much training time With Maxim as possible. OK?
Notified 1 person
Denis Slabakov
Sure
С уважением, Денис Слабаков
Notified 1 person
Jonny Andersen
Jan Erik stopped by and showed me what his prices are on all the parts that is required for water and sewage. His cost price is 73.069 + ca. 16.000,- in transportation (transported on two trucks). Jan Erik will sponsor the insulation for the pipes from kolodets to the building, if it`s needed. He uses the same plumber that will Connect the Office building, so they will be able to save some time in coordinating and work hours.
The reason is that in their first offer, the forgot to include SP1 as shown in the drawing from Norconsult.
I understand that this is frustrating!
But my priority right now is to get as much training time With Maxim as possible. OK?
С уважением,
Денис Слабаков
His cost price is 73.069 + ca. 16.000,- in transportation (transported on two trucks).
Jan Erik will sponsor the insulation for the pipes from kolodets to the building, if it`s needed.
He uses the same plumber that will Connect the Office building, so they will be able to save some time in coordinating and work hours.